The process will take around three months to complete

Main contractor Laing O’Rourke is overseeing the installation of 2,500 concrete piles for the foundations of Everton FC’s new 52,888-capacity stadium at Bramley-Moore Dock.

Table of Contents

The piling work, which began this week, is expected to continue until next summer. This will include foundations for the western stepped terrace that will overlook the River Mersey, Liverpool.

Infilling of the Grade II-listed, 10m deep Bramley-Moore Dock with more than 450,000m3 of fluidised sand began at the start of October. The process, aiming to provide a solid base across the site, will take around three months to complete.

The piling work is expected to continue until next summer

Providing a solid base across the site will take around three months to complete.

Infilling of the Grade II-listed, 10m deep Bramley-Moore Dock with more than 450,000m3 of fluidised sand began at the start of October. The process, aiming to provide a solid base across the site, will take around three months to complete.

While the infilling continues, foundation work has initially started on the north and south stands, where all the heritage assets have been removed and, where possible, are being preserved.

Danny Jones, part of the team overseeing the piling for the club’s construction partner Laing O’Rourke, explained: “We drill down to around 16m with a hollow drill, and, as we go, we pump concrete to the bottom through the stem to replace the bore with a column of concrete.

“We then place a reinforcement cage inside the bore, and this will form the foundations for the stands.

“In total, we expect to bore around 2,500 piles, each one being 600mm diameter and the deepest pile being 18m.

“They take around 4-6m3 of concrete per pile and, depending on the progress of the dock, we anticipate this work to be complete by the middle of next year.”

Designed to avoid the dock walls to prevent any damage to the listed assets

The piling layout is designed to avoid the dock walls to prevent any damage to the listed assets and to preserve them. Should the club decide to move the stadium in the distant future, it said the site could be reverse-engineered back into a dock.

The dock infilling will create a compacted and rolled surface, using sand dredged from the Liverpool Bay and the Irish Sea. This solid base will then be suitable for more piling, which will begin early next year and will form the substructure of the new stadium.

Historic England was against the infilling of the dock, as it believed it would “fundamentally change its historic character” and there was “lack of evidence” that it was necessary.

Liverpool City Council’s planning committee, however, approved the plans in February submitted by Everton Stadium Development, a subsidiary of Everton FC.

Largest single-site private sector development currently under construction in the UK.

The stadium development in Liverpool’s Northern Docks is recognised as the largest single-site private sector development currently under construction in the UK.

Related Articles you may like

Get SAP Air Tightness Certification UK
Get SAP Air Tightness Certification UK with Our Help

SAP air tightness certification checks how well a home keeps warm air in and stops draughts getting through gaps and cracks. We test this by using a fan to push or pull air through the building and measure how much escapes. If too much leaks out, your house will be harder to heat and cost more to run. We help builders and homeowners across the UK get their homes ready to pass this test, offering advice along the way. Once it passes, you get a certificate which is part of what’s needed to meet building rules and get an Energy Performance Certificate.

Read More »
MVHR
Do you need radiators with MVHR?

Are you looking for information about the MVHR (Modular Vapour Combustion Heat Recovery) technology? If so, read on for a useful guide to MVHR radiators. MVHRs are designed to heat homes without using radiators, but there are some factors you should be aware of. Here’s a look at what you need to consider before choosing MVHR products.

Read More »
SAP Calculations
What are L1B SAP Calculations For Dwellings?

SAP calculations are a way of comparing the running costs of dwellings anywhere in the UK. For new dwellings, SAP calculations are a simple desktop exercise, in which a client submits their specifications and plans to an assessor. They should be undertaken early on in the design process, as it can save a costly redesign of the dwelling.

Read More »